I
wrote a blogpost in July 2012, about the Rohtang tunnel being
excavated on a national highway of great importance, the Leh-Manali
Highway. I had explained in that blogpost the historical background
and the strategic necessity for which this highway was planned soon
after India's independence and work had began in 1950 itself. This
highway was opened to traffic in 1965, just after India-Pakistan war
for military transportation and later for everyone.
Manali-Leh
route travelling over 485 KM, is militarily safe because it is far
away from international borders. Because of this road, the life and
death importance of Kargil road to Ladakh has been reduced to quite
an extent. Even then, there remains one great obstacle on this
highway, which makes this road unusable during winter months. About
51 KM from Manali, this route passes through Rohtang pass, which is
at an height of 13000 feet. Because of very heavy snow fall in this
valley, the pass remains closed for at least 6 months a year. With
the pass remaining closed, road communications to Lahaul-Spiti araes,
which are just north of this pass and also to Ladakh, gets totally
blocked. Since both, Kargil and Ladakh route close in winter,
Ladakh's road connection with rest of the country is totally cut off
for 6 months every year. Even in summer, the weather in Rohtang pass
is unpredictable with cold biting winds and sub zero temperatures.
To
overcome this natural obstacle, the Indian Government flagged green
to a project of digging an all weather tunnel under Rohtang pass. In
1984, Geological Survey of India carried out the preliminary studies
and in 2000 the work on a road leading to Rohtang pass, costing 180
Crores Rupees(Rs. 1.8 Billion) was started at the hands of then Prime
minister Atal Bihari Bajpai . An Australian company , SMEC
International, was appointed as consultants for this work. After the
report of this committee was received, in September of 2009, the work
of building a tunnel under Rohtang pass was awarded to an
Indian-Austrian company, Strabag-Afcons, and the work commenced on 28
June 2010. Horse shoe shaped Rohtang tunnel is 8.8 KM long and would
have a width of 11.25 meters. Instead of using the old Rohtang-Leh
road, a new road passing thorugh Shin Kun pass in Zanskar valley and
Padm town in Zanskar, is also being built at the cost of 286 Crores
Rupees (Rs.2.86 Billions). All these works were expected to be
completed by 2015.
The
project met its first unexpected delay in form of a heavy ingress of
water through the rock face inside the tunnel in July 2012 and
presented a new challenge for Border Roads Organisation. Giant
boomers and heavy construction equipment had to be brought in to
control and deviate the steady flow of water that was not supposed to
have been there in the first place. The engineers and workers had to
work wearing masks, fluorescent jackets and knee-high rubber boots
had to wade through slush and water, under the glare of floodlights.
The
water ingress,spread over a small area and giving the impression of
miniature spring, at the rate of 35 litres per second, was flowing
into the tunnel at the last point of excavation at the south portal,
meaning that about 30.24 lakh litres of water, enough to fill up a
small lake, was entering the tunnel every day. According to
engineers the inflow was unexpected as the rock survey did not
reveal any such water presence at this point. In desperation, BRO
resorted to chemical grouting using polyurethane procured from
Switzerland, rock bolting and pipe umbrella roofing, which involved
boring steel rods and mesh, to strengthen and stabilise the overhead
rock. The Swiss chemical was expensive and about 4.5 tonnes, costing
about Rs 35 lakh, was used. Due to the ingress of water, the project
was running roughly 300m behind schedule in July 2012.
After
2012 incident, as per my knowledge, no further delay has been
reported by BRO. But local press reports say that the project would
now be completed only in 2017. This delay has made people in
Lahaul-Spiti district of Himachal Pradesh state of India, restless
as, this tunnel, which they call as tunnel of hope is really
something on which their entire future depends.
Lahaul-Spiti
district,spread over 13833 square km but with a population of 31,528,
has the lowest population density of 2 per sq km in country. Their
only contact with rest of the country is through Kullu, that too
after crossing the 13050-foot-high Rohtang pass. So during winter
months, the tribal district is cut off from the rest of the world in
late October or November following heavy snowfall and opens up only
in April or May after snow is cleared from Manali-Rohtang-Keylong
road. People resent this cut off because during winter months, even
the helicopter service faces problems and it becomes impossible to
get specialized medical treatment. Completion of tunnel was expected
to propel tourism business in Lahaul-Spiti but now people would have
to wait longer to witness the tourism boom and fulfillment of their
dreams
The
Rohtang tunnel has already become a dream of the lifetime and a lifeline for Lahaul residents, even before its completion. So
high are the hopes! To meet the challenges of the mammoth task, the
BRO has brought in an array of hi-tech and automated equipment, much
of which is imported and some of which is being used for the first
time in India. But if unexpected problems arise like ingress ofd
water in 2012, there is very little BRO can do. Residents of
Lahaul-Spiti district may have to wait for couple of more winters
before their life line opens for them.
20th
August 2014
p.s. As reported in Border Roads Organization, Annual Chief Engineers Conference, 2014, out of total length of 8.8 Kms, 4.4 Kms length of tunnel has been completed by September 2014. The completion date has now been pushed forward to 2017.
9th July 2015
p.s. As reported in Border Roads Organization, Annual Chief Engineers Conference, 2014, out of total length of 8.8 Kms, 4.4 Kms length of tunnel has been completed by September 2014. The completion date has now been pushed forward to 2017.
9th July 2015
Great work.
ReplyDelete